Progress on site has been a lot since I visited 4 weeks ago.
- elections and plumbers have started on the C-units
- Roof framing is almost complete at the high street block, and roofing is expected to be completed by the end of this month
- Two of the D-units have their internal staircase in
- Alva Street has its 1st first floor down (A6). Most bottom plates are down, which means the sips will be going up quickly
- All of Alva Street has scaffolding up, which gave us a real sense of how beautiful and big our common court yard will be
- The tent is expected to be taken down by the end of this month
I also attended the first on site contractors meeting, to coordinate and raise questions between builder, plumber, electrician, and ventilation install.
Enjoy the sun and see you all next week. Rainer