Hi all
A brief report on the important and interesting things.
specific client requests: we agreed in principle about a system whereby S&W quote and the client prepays UCOL for the job. To be discussed by the BCG and Nicola.
S&W stressed that the service trench will be opened after Easter and that we have to have a plan in place for the Fibre connection very soon.
I hope to be at next weeks meeting with Chorus and that we can email out a recommendation on how to proceed.
The first third of the high street block will have the concrete poured on Monday!!
S&W were not faced by a request for a site visit, but we all agreed it will be more interesting in a few weeks. Our next site meeting is in 4 weeks and we will talk about then.
The first shipment of windows, mainly for Alva Street has arrived and is stored in our workshop, behind the locked new garage door. They look great, are apparently very heavy (triple glazed!), and the windows and doors are big! Ps the outside frame is black (see parts where the protective film has been peeled away on the door in the picture). The inside frame is off white.
Regards Rainer