Resending this through this email as some people didnt received it from the other account on friday. Sorry if you got it twice.
Thanks,
Maria
Begin forwarded message:
From: Maria Callau maria@sur-architecture.com Subject: Fwd: Site visit update 15Feb19 Date: 17 February 2019 at 12:01:28 PM NZDT To: Maria Callau maria@sur-architecture.com
Begin forwarded message:
From: High St Cohousing <ucolbuild@gmail.com mailto:ucolbuild@gmail.com> Subject: Site visit update 15Feb19 Date: 15 February 2019 at 5:02:20 PM NZDT To: UCOL shareholders <ucol-shareholders@list.king.net.nz mailto:ucol-shareholders@list.king.net.nz>
Hi everyone.
A quick update from our site visit today.
GROUND CONDITIONS A completed schedule of quantities has been received and sent to Rawlinsons for review and comment. Their feedback is expected by early next week, before our PCG meeting (Tuesday).
S&W approached two other contractors for pricing but were not able to do the work in the next few weeks (only in 8 weeks time).
Halls Brothers is the only one that can do the work, starting around the 20th of this month (if notified by next week). We could expect work done by the end of March. Rawlinson is currently reviewing their $ to ensure that they are acceptable numbers and will provide us with their recommendations before Tuesday.
An indicative cost was discussed based on the numbers provided by Halls Brothers which comes just below the 200K… There are few costs that need to be added to that number: Costs of supervision / Goetech / Testing equipment / Archaeologist, etc.
- the design cost already invoiced to us (but not paid yet) from Engineers and Geotech for work done in December and January (around 19K).
SIPs The first deliver of SIPs panels have arrived on site. A lot of work underway in the common house.
See pictures below and have a great weekend!
Maria
Maria Callau UCol member and Coordinator Architectural Graduate 0211847490
High St Cohousing
SIP on site
Guest Rooms:
Kitchen
Workshop
M2
M3
M2/M3
WORKSHOP - GARAGE DOOR
M2
M3
M1