I thought I would update people with what I have heard about
possible moving dates and early access arrangements so far. The
directors will discuss most of this tomorrow at our meeting, and
on Friday there will be a site meeting that may give us a better
handle on the finish date.
Settlement Date
In the mean time, I believe the earliest date we might settle, as
already discussed, would be the 12th of March. This is
what people should be telling their banks and Kiwisaver.
The factors that influence the date are:
- Stevenson & Williams and subcontractors finishing the
build (Practical completion). Stefan our project manager says
"they're very close" but they aren't saying when, and did not
provide us with an updated work program. So my guess
is this could take anything from another week to another month
to finish, putting the finish date between the 24th of February
and the 12th of March.
- Issue of titles. There are no formal timeframes for this, but
the lawyer says they have been taking about 3 weeks. This was
applied for last week, so our best guess is it will be ready
around the 5th of March.
- Issue of code compliance by the DCC. This has a statutory
limit of 20 working days (plus extra time for council queries)
once we apply, but we won't be ready to apply until the major
outstanding siteworks are done, at least a week away before we
can even apply. Stefan says though the council will probably be
quick and issue code compliance within a few days of applying.
My guess for the earliest date we could get this would
be around March 3rd, if the siteworks and the council process
both happen quickly. (There is no limit to how long this might
take, if we run into problems with the kerbing for example and
that took a month to sort out, then the council was slow and
picked up some defects that needed to be remedied for
compliance, then it could push that out until April or even
May.)
- The time for lawyers (and purchasers and their banks) to
prepare for settlement. This is currently set at 10 days (after
the later of title and code compliance) in our Sale and Purchase
contracts, so if both of those come through by March 5th
(remember that's optimistic), then settlement would be set at
March 15th. HOWEVER, the contract also says that if we all
agree, then we can alter the settlement date, e.g. we could make
it just 3 days after we receive code compliance if we wanted.
So the earliest possible settlement date (allowing for the
weekend) would be March 10th. This will need a resolution
signed by all purchasers, and to convince everyone's lawyers to
do it.
- The time for Kiwisaver funds to be ready. Since (I assume)
people who need this are telling Kiwisaver funds the settlement
date is March 12th, we won't be able to settle before that date.
So you can see that the earliest possible date for settlement
would be March 12th, and a pessimistic scenario would put
settlement in May. And we will be in a position to give a better
estimate after Friday. But don't wait to make sure everything you
need as a purchaser is prepared for a possible March 12th
settlement.
Early access
The admin group have not met again yet. Information collected by
Marianne shows 11 out of 24 units want to do their own painting
and fixtures (10) and/or or store gear in their units (2). It
will be very much easier to paint before we move gear in. Not
everyone will need to do this before settlement though. It seems
like probably 5 - 8 units would be very keen to have that access
before settlement, the others could probably be flexible and do it
after settlement.
It also looks like around 9 units want to arrange access for
contractors (or themselves) to do work before settlement, for
wardrobes, curtains and painting.
Remember, contractors can already be doing work from now if they
get an arrangement for access. I assume people who need this have
already talked to someone on the PCG?? and it is underway.
If we want to do our own work before settlement, it has to happen
after practical completion, and there will likely be at least a
week of opportunity for that. We still need to sort out what we
need to do to make sure all stakeholders are comfortable with
this.
Unit Inspections
You will be able to do an inspection of your unit before
settlement, per normal practice when buying a house. We will
likely discuss this more at the next group meeting. Again it will
be after practical completion and before settlement.
UCOL To-Do list
- Arrange an agreement and any other required documentation
(e.g. shareholders or director's resolutions) to shorten the
lead time to settlement from 10 days, should we want to do that.
- Work out how to make sure stakeholders are comfortable with
early access for finishing work, and storage.
- Arrange for unit inspections.
Thanks,
Alex