Hi all, no photos today :(
Things are moving along and it is 2 weeks to the Christmas brake on site.
The first High Street units C and D have all their plumbing and electrical wiring in place. And all units have their stairs in.
They are working on the ground floor sips of A5, I think they want to reach the end of the Alva Block before Xmas. The first 3 Alva units have their first floor in.
Will be an exciting site visit in a week on Friday and Saturday!
See you Thursday Rainer