Hi all
Progress on site has been a lot since I visited 4 weeks ago.
elections and plumbers have started on the C-units
Roof framing is almost complete at the high street block, and roofing is expected to be completed by the end of this month
Two of the D-units have their internal staircase in
Alva Street has its 1st first floor down (A6). Most bottom plates are down, which means the sips will be going up quickly
All of Alva Street has scaffolding up, which gave us a real sense of how beautiful and big our common court yard will be
The tent is expected to be taken down by the end of this month
I also attended the first on site contractors meeting, to coordinate and raise questions between builder, plumber, electrician, and ventilation install.
Enjoy the sun and see you all next week. Rainer