Hi Everyone
It was very cold and wet on site this morning!
The builder is disappointed with the weather, especially since they had started with the roofing...
Progress on site:
roofing started on the high street block windows and doors are being installed on the first floor level. The second part of the Alva Street Block will have the concrete poured very soon The first bottom plates are down on the Alva Block, which means we should see the first Zips going up there soon! Stay dry!
Regards Rainer
Please call me if you need an urgent reply.
Rainer Beneke +64 21 144 7700
ucol-shareholders@list.king.net.nz