Hi all,
Just a quick update on the project status as I understand that a few people
are wondering when they can have access to finish their units.
Friday was SWs last day on site, they have removed all their belongings,
etc.
This week, there are still a few contractors doing some work on site and
Tim is doing the second defects inspection (common areas and M units).
Paperwork for *Practical Completion* is underway (Stefan and SW are sorting
out things).
Once Practical Completion Certificate is issued, we need our own body corp
insurance to take place.
Once that is done, SW have a few weeks to address the defects list, so they
will be going back to fix/adjust things in the list.
But the site will be under our management, they will have access to do the
work but it is our responsibility to have insurance in place.
Final Inspection went well on Friday with paperwork being sorted to apply
for *Code of Compliance* soon.
Tomorrow the ADMI group will meet at 5:45 at the common house to plan our
steps forward.
After our meeting we will be reporting to the group on steps and dates
planned for individuals to organise painters, wardrobes, curtains, etc.
Thanks,
Maria
--
*Maria Callau*
*TOIORA* High Street Cohousing
UCOL Member and Project Coordinator
0211847490